Council leader defends Northumberland Line rising costs as extra £37.8m approved
The leader of Northumberland County Council has defended the flagship Northumberland Line project, despite the need for an additional £37.8 million in funding to get the scheme over the line.
Members of the council’s cabinet approved plans for the increase on Wednesday, bringing the total cost of the project to £336.4 million.
The cost increase has been blamed on engineering challenges around unmapped mineworks, particularly at the unopened Northumberland Park station.
The county council will fund £10 million while the Department for Transport has agreed to provide an additional £17 million. The cabinet has now agreed to submit a request to the North East Combined Authority for the remaining funding.


Stations at Bedlington and Blyth Bebside are also yet to open to the public, but are understood to be nearing completion.
Council leader Glen Sanderson said: “I have written to the Secretary of State for Transport to ask for more carriages for the Northumberland Line. This is not a simple process – in fact it is quite the opposite and requires a huge amount of bureaucracy which I’m sure is absolutely necessary.
“The Northumberland Line has been far more successful than anybody imagined, and this is about ensuring the line is capable of taking the passengers who want to use it. We don’t want to see a situation where demand outstrips supply of trains.
“We have seen over 500,000 journeys since the middle of December. If that continues, we could reach our millionth passenger within the next six to nine months.
“Who knows how successful we will become like this? We need to build on the success we have had.
“We’re nearly at the end of the line in terms of the project.”
The line, which runs from Ashington to Newcastle via Blyth, Bedlington and Seaton Delaval, was closed to passengers in the 1960s as part of the Beeching cuts.
Cllr Sanderson added: “We’re finding the money within the county council in order to do this. I’m grateful to the Government for continuing to support this and I welcome the enthusiasm of the combined authority supporting this.
“This is a great success story and I’m incredibly pleased we had the courage and ambition as a Conservative council to get this done.”