Rail services to be disrupted between Edinburgh and Newcastle on three consecutive weekends due to engineering works
A £4.6 million project to improve the reliability, resilience and long-term performance of the East Coast Main Line (ECML) will get underway next month.
The work happening between North Berwick and Dunbar will help to keep trains running smoothly for years to come on the line.


To allow engineers to carry out improvements safely and efficiently, the line between Edinburgh and Newcastle will be closed from Saturday 19 September to Monday 21 September and from Saturday 26 September to Monday 28 September.
During the works, 1km of track will be renewed at Hedderwick and new drainage systems installed with rails being replaced at Ninewar.
A project to stabilise a slope at Howburn, near Reston, will also be delivered.
On the following weekend, Saturday 3 October and Sunday 4 October, engineering work will also be taking place between Newcastle and Berwick.
During these closures, services operated by LNER, ScotRail, LUMO, CrossCountry and TransPennine Express will be affected, with rail replacement transport and some alternative rail travel options available.
Ross Moran, route director at Network Rail Scotland, said: “This is an important investment in the East Coast Main Line, helping us deliver a more reliable railway for passengers and freight customers.
“We know the closures will be inconvenient for some passengers, and we'd like to thank them for their patience while this work takes place.
“By closing the line over weekends, our engineers can carry out a significant amount of work safely and efficiently, reducing the need for future maintenance and keeping the railway running smoothly for years to come.”