Northumberland Street latest explained as delayed regeneration gets 'finishing touches'
Council chiefs say that “finishing touches” are all that are needed to finally complete the long-running transformation of the North East’s busiest high street.
Northumberland Street, in the heart of Newcastle city centre, has been undergoing major refurbishment works since December 2023.


The multi-million pound project has included the addition of 50ft ‘Pilgrim Pole’ lighting pillars, new seats and trees being installed, and repaving.
It was due to be completed in summer 2025, but is now a year delayed after encountering delays blamed on the complex patchwork of utilities found beneath the street.


Newcastle City Council has now confirmed what work is actually left to complete.
Shoppers will have noticed that several sections of Northumberland Street remain fenced off despite the restoration scheme supposed to be near its end.
Much of that safety fencing has been around areas where sealant around new paving stones is being finished off this week, to prevent the surface being damaged by members of the public walking over it.
A sixth and final Pilgrim Pole, designed to represent the markers which guide people across to Holy Island, also needs to be installed at the Blackett Street end of the busy shopping area.


That work was delayed due to the uncovering of high-voltage utility cables beneath its intended location, but foundations for the lighting column have now been laid and it will be erected over the next few weeks.
Once that is done, the only outstanding work will be the final power connections to the street that will enable the Pilgrim Poles to be switched on.
Lib Dem councillor Owen Burbidge, the council’s cabinet member for inclusive economy and skills, said: “Northumberland Street’s transformation is now in its final stages, with the vast majority of works complete and only finishing touches remaining.
“Our administration took office in May with this project already nearing completion, and our focus is on supporting the project team and partners to ensure the remaining works are delivered as quickly and safely as possible, and to the high standards that we have seen throughout. We look forward to seeing the final elements completed so that residents, businesses and visitors can enjoy the full benefits of this investment.
“The street is very much open for business and people are already enjoying its new look and feel. New seating has been installed throughout, increasing capacity almost fourfold to provide more than 90 places to sit, relax and socialise in comfort.
“We’ve introduced rain gardens planted with a variety of flowers and grasses, creating an attractive new feature with sustainable drainage that will improve the street’s resilience. Twenty-two new trees have been planted, carefully selected for their seasonal interest and long-term contribution to the city centre environment.
“The street has been fully repaved using a high-quality design inspired by Newcastle’s medieval heritage, alongside major upgrades to essential infrastructure to future-proof this important city centre space.”
Northumberland Street was historically part of the ancient route to Lindisfarne and the pattern of newly-laid paving stones along the centre of the street is inspired by the Lindisfarne Gospels tapestry.
Cllr Burbidge added: “Five of the six Pilgrim Poles are now in place and, together with the other new lighting, are already enhancing the character of the street. The foundations for the final pole at the Blackett Street end are now complete and installation will start from next week.
“Some temporary barriers will remain in place while final works are completed, moving along the street in sections and being removed as soon as possible. The only remaining works beyond this relate to final power connections being delivered by utility suppliers.
“This is one of the most significant public realm improvements ever undertaken on Northumberland Street, creating a greener, more accessible and welcoming destination with many more places to sit, spend time and enjoy the city centre. I’d like to thank businesses, residents and visitors for their patience and look forward to seeing people enjoy the street for many years to come.”