Changes planned to layout of Maltings theatre and cinema in Berwick ahead of £25.9m rebuild
A series of changes have been made to the design of the new Maltings venue in Berwick.
A reconfiguration of the internal space is now proposed with the theatre moved to be on the same level as the access off Eastern Lane.


It will also mean some minor changes to the exterior which the project team hope will address some of the criticism levelled at the £25.9m proposal before it received planning approval in August.
There were 157 letters of objection, along with 251 in support, while the Berwick Heritage campaign group gathered a 1,000-signature petition voicing concern at the changes to the skyline.


The proposed changes mean a new application seeking permission to modify the plans will be submitted soon with the public invited to have their say.
Damon Barnaby, senior project lead, said: “We have made some really good progress. The architects have brought a fresh perspective to it and worked really hard to make some improvements. There’s now a much better flow to the building and it’s a better fit to the townscape.”
A drop-in event was held at Berwick Workspace on Monday to give local residents a chance to meet the team and see the changes.
The design tweaks will bring the main theatre, cafe bar and dining spaces together on the same floor and maximise views across the River Tweed.
On the level above there will be further public spaces, while a mezzanine floor above the bar ‘allows the atmosphere of the main foyer to drift up’. A rehearsal space and meeting room lead off this space.
The lower floors will be repurposed to create one large main cinema and a smaller boutique cinema, accessed directly from Shoe Lane and via a lift from the car park level.
The building will be fully accessible with a new ramped entrance from Eastern Lane and lifts between all floors.
Contractors Willmott Dixon Construction have been appointed under a Pre-Construction Services Agreement to develop the design.
Robin Stewart of Newcastle-based architects NORR said: “The overall scale and mass has not changed but there have been subtle changes to break up the facade and make it look more sympathetic.
"Internally, it’s far better for accessibility, there are more toilets, it’s far better for back stage access and the cafe bar area now makes the most of the fantastic views.”
It is envisaged it will go to the planning committee in the spring with the main works due to start in early summer and a completion date of early 2028.
A temporary cinema has opened at the Berwick Barracks site, using the Mob Store. Once The Maltings itself is completed, the Mob Store will become the new permanent home of the Northumberland Archives.
The Maltings project funded through the Borderlands Inclusive Growth Deal is the latest in a number of major investments in the town over recent years – including a new £35million hospital under construction, a £23million leisure centre, a £4.2million project to create a thriving cultural hub at Berwick Barracks and a planned new £50million high school.