Bridge strengthening works in Northumberland village to get underway soon
Works to strengthen a bridge near Morpeth are due to get underway next week.
Tranwell South Bridge, in the village of Tranwell, will undergo repairs from July 8, lasting around nine weeks.


The bridge carries the C150 link road over the Catch Burn and it currently has insufficient capacity to accommodate the weight of some modern vehicles.
The works involve the excavation of the carriageway material and the installation of a reinforced concrete strengthening slab above the existing structure. The carriageway will then be reinstated, alongside drainage and parapet improvement works.
Due to the nature of the works, the road carried by the bridge will be required to be fully closed and a 2.5-mile diversion route will be in place via the B6524.
Paul Jones, director of environment and transport at Northumberland County Council, said: “We are sorry for any inconvenience, but these works will ensure the bridge is fully strengthened and improved for years to come.
“We thank drivers in advance for their patience.”